代写建筑工程职称论文:超高层建筑主体施工测量方案及层间垂直度控制方法

发布时间:2011-06-29 13:34:34 论文编辑:代写论文网

    [摘要]广州珠江新城西塔工程主体采用筒中筒结构,为超高层建筑,施工测量和层间垂直度精度控制难度较大。较详细地叙述了超高层建筑主体施工测量方案,包代写建筑工程职称论文括提模钢平台顶面主要轴线控制,轴线竖向引测方法和放线步骤。关于主体建筑的主要控制轴线竖向引测及钢模板定位技术具有创新性。同时指出施工测量具体流程,分析了层间垂直度控制及其要求,使结构各项指标符合工程要求。

    [关键词]垂直度控制;提模钢平台;激光垂准仪;施工测量

      Abstract: Guangzhou Pear River New Town West-tower with a tube-in-tube structure belongs to super high-rise building.It is difficult to control the construction survey and interlayer verticality precision between the floors.The authors describe the main body of super high-rise building construction measurement schemes in detail,such as the control of main axis in steel platform top surface for hoisting template,the methods of axis for vertical measurement and the steps of setting out.It has innovation in the control of vertical measurement about mainly axis and steel template location.Idiographic flow of construction measurement is put forward as follow,analyzing vertical precision between the floors and its requirement,then the various index accord with engineering requirements.

      Key words :verticality control;steel platform for hoisting template;laser verticality machine;construction survey

1  工程概况
      广州珠江新城西塔工程位于珠江新城珠江大道西侧、花城大道南侧,毗邻富力中心和第二少年宫。总建筑面积45万m2,副楼28层,高100m,主塔楼103层,高437m。主体为筒中筒结构:外部为钢管混凝土巨型斜交网格柱外筒,内部为六角形钢筋混凝土核心筒;副楼为框支剪力墙结构。

2  施工测量方案
      2.1提模钢平台顶面主要轴线控制提模钢平台顶面主要点位布置如图1所示。
      2.2轴线竖向引测方法当主塔楼施工至第10层时,核心筒已经安装钢平台进行提模施工,原外控放线方法已不适用,必须采用轴线竖向引测方法。每12层(54m)进行一次竖向投测控制点转换(见图2)。
      在核心筒外六角测量(转换)控制点上架设垂准仪,将轴线控制点引测至钢平台顶部平面上,在已经安装的强制对中架上架设全站仪,经过内角闭合检查、边长检测复核,采用坐标法放线,放出如图1所示主要轴线控制点36个,然后采用手持激光给向仪控制模板安装定位。 
每层核心筒剪力墙施工至少引测3个外六角点至钢平台顶面,校核后采用坐标法放线;每施工3层剪力墙至少引测一次全部6个外六角点至钢平台,进行全部内角和边长检查后再放线。
      2.3放线步骤
      1)每层墙体混凝土浇筑时,在低于混凝土面200mm处预埋带有套筒的钢筋(套筒口要用塑料封住),每面墙体需预埋3个(或2个)套筒钢筋,总计48个预埋件(见图3)。
      2)钢模板提升后,去除套筒处的塑料,接入供放置激光给向仪和轴线标记并焊有钢板的横向钢筋。钢筋拧紧后应保持钢板基本水平,以便放置激光给向仪时其垂直代写建筑工程职称论文自动补偿功能满足控制模板要求;若钢板难以置平,则需往套筒里填塞软垫,再拧紧钢筋(见图4)。
      3)通过钢平台上放出的墙体控制轴线和特制横向标尺(需透明),确定钢模板底部定位的理论轴线位置。
      4)操作者在钢模板底部横向钢筋上放置手持激光给向仪,且其处于铅垂状态,并发出光束;手持激光给向仪瞄准横向标尺的理论轴线位置,在横向钢筋上标记钢模板定位实际位置(见图5)。
      5)根据第4步操作确定的竖向垂直激光束,调整钢模板使其处于铅垂状态,模板定位即完成。3  施工测量流程(见图6)

4  层间垂直度控制分析
      按上述方案确定的轴线控制点竖向传递路径,核心筒剪力墙体(钢模板)定位累计误差由以下4项组成。
      1)按提模钢平台顶面主要轴线控制点布置图,进行竖向投测用的六边形控制点(编号为1,3,5,7,9,11)是采用四等闭合导线级别观测平差后确定的点位平面坐标,其点位中误差最大为3.2mm。
      2)采用JZC激光垂准仪竖向投测,最大投测高度以80m计(按专项方案要求,控制点每54m转换一次,加之提模钢平台及其挂架高度),仪器精度为1/200 000,激光垂准仪对中误差为0.5mm,投测误差为80 000/200 000+0.5=0.9mm。
      3)轴线控制点投测到钢平台顶面后,采用1″级精度以上全站仪坐标法放线,最大放线距离为30m,其放线误差为3.0mm。
      4)手持激光给向仪确定钢模板位置,其误差为3.0mm。以上4项合计总误差为:M=±(3.22+0.92+3.02+3.02槡)=±5.4mm,满足规范±8.0mm的要求。

5  垂直度控制要求
      1)垂直向上投测的控制点必须3个以上,经过距离、角度闭合后才能放线。
      2)利用全站仪在钢平台上放样剪力墙控制轴线后,应变更测站对所放点位坐标进行检查。
      3)竖向投测所用控制点需定期进行水平位移检测。
      4)竖向投测点位保留在模板上口并拉通线,以便模板校正。
      5)在模板定位的质量检查验收时,需把偏差较大的模板校正后再报监理单位复核。

6  结语
      1)超高层建筑施工测量,当建筑物高度≥150m,垂直度控制精度与建筑物的刚度关系很大;标高控制时应考虑建筑物的压缩变形。
      2)测量仪器宜选用1″级以上全站仪和精度1/200 000激光对中的激光垂准仪。
      3)基于进度控制需求,在照明条件良好情况下,夜间可以进行建筑物内部竖向轴线引测及施工放样测量。
      4)测量定位整个工序组织应该自外围高等级控制开始直至模板定位及其检查验收完成,归属一个垂直组织系统管理。

参考文献:/
    
 [1]邓少云.内控法在高层建筑施工测量中的应用[J].株洲工学院学报,2003,(2):108-110.Deng Shaoyun.Application of inner control method to theconstruction measurement of skyscraper[J].Journal of ZhuzhouInstitute of Technology,2003,(2):108-110.(in Chinese)
[2]黄周才.复杂体型高层建筑施工测量质量控制[J].广东土木与建筑,2005,(9).Huang Zhoucai.Quality control of construction survey for highbuilding with complicated shape[J].Guangdong ArchitectureCivil Engineering,2005,(9).(in Chinese)
[3]张峰,何凯锋.高层建筑的施工测量与控制[J].铁道勘察,2005,(6).Zhang Feng,He Kaifeng.The construction survey and monitoringof high buildings[J].Railway Investigation and Surveying,2005,(6).(in Chinese)
[4]周继忠,蔡雪峰,聂小龙.高层建筑施工测量质量控制[J].福建建筑,2005,(2).Zhou Jizhong,Cai Xuefeng,Nie Xiaolong.The quality control oftall building construction measurements[J].Fujian Architecture&Construction,2005,(2).(in Chinese)
[5]余学祥,吕伟才.GPS自由网平差坐标的转换[J].勘察科学技术,1999,(2).Yu Xuexiang,LüWeicai.Transformation of GPS free netadjustment coordinates[J].Site Investigation Science andTechnology,1999,(2).(in Chinese)[6]中国建筑科学研究院.JGJ3-2002高层建筑混凝土结构技术规程[S].北京:中国建筑工业出版社,2002.China Academy of Building Research.JGJ3-2002 Technicalspecification for concrete structures of tall building[S].Beijing:China Architecture&Building Press,2002.(in Chinese)
[1]邓少云.内控法在高层建筑施工测量中的应用[J].株洲工学院学报,2003,(2):108-110.Deng Shaoyun.Application of inner control method to theconstruction measurement of skyscraper[J].Journal of ZhuzhouInstitute of Technology,2003,(2):108-110.(in Chinese)
[2]黄周才.复杂体型高层建筑施工测量质量控制[J].广东土木与建筑,2005,(9).Huang Zhoucai.Quality control of construction survey for highbuilding with complicated shape[J].Guangdong ArchitectureCivil Engineering,2005,(9).(in Chinese)
[3]张峰,何凯锋.高层建筑的施工测量与控制[J].铁道勘察,2005,(6).Zhang Feng,He Kaifeng.The construction survey and monitoringof high buildings[J].Railway Investigation and Surveying,2005,(6).(in Chinese)
[4]周继忠,蔡雪峰,聂小龙.高层建筑施工测量质量控制[J].福建建筑,2005,(2).Zhou Jizhong,Cai Xuefeng,Nie Xiaolong.The quality control oftall building construction measurements[J].Fujian Architecture&Construction,2005,(2).(in Chinese)
[5]余学祥,吕伟才.GPS自由网平差坐标的转换[J].勘察科学技术,1999,(2).Yu Xuexiang,LüWeicai.Transformation of GPS free netadjustment coordinates[J].Site Investigation Science andTechnology,1999,(2).(in Chinese)[6]中国建筑科学研究院.JGJ3-2002高层建筑混凝土结构技术规程[S].北京:中国建筑工业出版社,2002.China Academy of Building Research.JGJ3-2002 Technicalspecification for concrete structures of tall building[S].Beijing:China Architecture&Building Press,2002.(in Chinese)
[1]邓少云.内控法在高层建筑施工测量中的应用[J].株洲工学院学报,2003,(2):108-110.Deng Shaoyun.Application of inner control method to theconstruction measurement of skyscraper[J].Journal of ZhuzhouInstitute of Technology,2003,(2):108-110.(in Chinese)
[2]黄周才.复杂体型高层建筑施工测量质量控制[J].广东土木与建筑,2005,(9).Huang Zhoucai.Quality control of construction survey for highbuilding with complicated shape[J].Guangdong ArchitectureCivil Engineering,2005,(9).(in Chinese)
[3]张峰,何凯锋.高层建筑的施工测量与控制[J].铁道勘察,2005,(6).Zhang Feng,He Kaifeng.The construction survey and monitoringof high buildings[J].Railway Investigation and Surveying,2005,(6).(in Chinese)
[4]周继忠,蔡雪峰,聂小龙.高层建筑施工测量质量控制[J].福建建筑,2005,(2).Zhou Jizhong,Cai Xuefeng,Nie Xiaolong.The quality control oftall building construction measurements[J].Fujian Architecture&Construction,2005,(2).(in Chinese)
[5]余学祥,吕伟才.GPS自由网平差坐标的转换[J].勘察科学技术,1999,(2).Yu Xuexiang,LüWeicai.Transformation of GPS free netadjustment coordinates[J].Site Investigation Science andTechnology,1999,(2).(in Chinese)[6]中国建筑科学研究院.JGJ3-2002高层建筑混凝土结构技术规程[S].北京:中国建筑工业出版社,2002.China Academy of Building Research.JGJ3-2002 Technicalspecification for concrete structures of tall building[S].Beijing:China Architecture&Building Press,2002.(in Chinese)